Building permit calculations can be difficult at times as there may be many variables involved in some projects. The methods and fees below are general guild-lines for permit fee calculations. However, the permit fee amount will ultimately be determined and set by the Code Official!   

Building Permit Calculation Method
Based on the International Code Council's Building Valuation Data - August 2009

New Construction

Gross Area x Construction Cost x Fee Multiplier of .0056
Example (1500 sq.ft. home x $100.00 per sq. ft. x .0056 = $840.00)

Alterations/ Renovation to existing Residential dwellings
Gross Area x Construction Cost x .25 x Fee multiplier of .0056
Example (1500 sq. ft. home x $100.00 x .25 x .0056 = $210.00)

Square Footage Permit Fee Calculator based on the method above.
MULTIPLIER UPDATED 09/08/2021 OFF 08/18/2021 FEE SCHEDULE BY MICHAEL A. BURSEY

2021 Building Permit Fees_Page_1
FEE SCHEDULE FOR 2021 UPDATE PLACED ON SITE 09/08/2021

Water Connection (Tap) Fee

 Water Connection Fee - New   Fee
 3/4" Service Line Tap   $200.00
 1" Service Line Tap  $250.00
 1 1/2" Service Line Tap  $400.00
 2" Service Line Tap  $600.00
 3" Service Line Tap  $800.00
4" Service Line Tap  $1,000.00
 6" Service Line Tap  $1,500.00
 8" Service Line Tap  $2,500.00
 10" Service Line Tap  $3,000.00
   
Water Connection Fee (Existing Service Line) $25.00
   
Water off/on Fee (Existing & New Service Line) $25.00
   
Water Late Payment 10%
   
Water Deposit $100.00

 
Sewer Connection (Tap) Fee

 Sewer Connection Fees - New   Fee
 4" Lateral   $250.00
 6" Lateral  $375.00
8" Lateral  $500.00
Sewer Replacement Inspection Fee $25.00